If you save your project and the tasks have for instance a Finish to Start precedence relationship they will follow... You must not have a precedence releationship linking the tasks
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
Anonymous
Anonymous
-
2022-03-16
Ref. attached image, task 18 has task 17 as a predecessor. You can see the problem
If you save your project and the tasks have for instance a Finish to Start precedence relationship they will follow... You must not have a precedence releationship linking the tasks
Ref. attached image, task 18 has task 17 as a predecessor. You can see the problem
Just found the update option......all good now